Mozambique Compact Monitoring & Evaluation
Projected Results by End of Compact
The Mozambique Compact aimed to achieve the results below by the end of the compact in September 2013:
- Reduce the poverty rate by up to 10% in Northern Mozambique (Provinces of Cabo Delgado, Nampula, Zambezia, and Niassa);
- Increase annual household income by up to $62, and
- Reduce the incidence of stunted children under the age of 5 by 13%.
Results to Date
Information on results to date is available in the Table of Key Performance Indicators (a subset of the full set monitored under the Mozambique Monitoring and Evaluation Plan). The full set of performance indicators is detailed in the final Monitoring and Evaluation Plan.
Impact Evaluation Framework
MCC carefully monitored implementation performance and the measurement of preliminary results. MCC funded several independent evaluations to assess what would have happened in the absence of the MCC investments, and to measure impacts specifically attributable to MCC-funded activities.
Read more about the evaluation of the Rural Water Supply Activity, the Farmer Income Support Project, and the ongoing Urban Land Regularization and the Land Administration evaluations. More information is available in the final Monitoring and Evaluation Plan.
Projected Long Term Results
Timeframe | Estimated Beneficiaries | Estimated Benefits |
---|---|---|
Not specified |
2,684,796 Any household expected to receive an income gain from the MCC project, either through direct monetary increases, time savings, land value. |
$120,970,000
Net Benefits are the compact benefits minus the costs for the project(s) over the 20 year compact life. This is calculated at a 10% discount rate. |
Projected Long Term Results by Project
Project | Estimated Beneficiaries | Estimated Benefits |
---|---|---|
Farmer Income Support Project ObjectiveThe objective of the Farmer Income Support Project was to improve productivity of coconut products and encourage diversification into other cash crop production. |
534,044 | $43,050,000 |
Land Tenure Services Project ObjectiveEstablish efficient and secure land access for households, communities, and investors. |
1,333,445 | $38,840,000 |
Rehabilitation/Construction of Roads Project ObjectiveIncrease access to productive resources and markets while reducing transport costs. |
1,237,734 | $-13,280,000 |
Water and Sanitation Project ObjectiveIncrease access to reliable drinking water supplies and improved sanitation. |
780,908 | $52,360,000 |